transfer batch and Overlap quantity have no effect on scheduling

(0) ShareShare
ReportReport
Posted on by

Hi,

I hope someone can help me,

I am trying to set up a route for a formula item where two operations are in sequence but they have an overlap.

The second operation can start as soon as 1 pcs is produced in the first operation.

I have set the transfer batch to 1 in the route, and in the production route the overlap quantity is set to 1 after estimation ( good sign i think)  but when I schedule the jobs they stay in sequence and there is no overlap.

Do I need to set something else, I thought transfer batch was enough.

*This post is locked for comments

I have the same question (0)
  • Verified answer
    Community Member Profile Picture
    on at
    RE: transfer batch and Overlap quantity have no effect on scheduling

    Hi, Got it to work

    Needed to set the overlap parameters on the route group.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Abhilash Warrier – Community Spotlight

We are honored to recognize Abhilash Warrier as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Martin Tocauer Profile Picture

Martin Tocauer 4

#2
Community Member Profile Picture

Community Member 2

#2
Nayyar Siddiqi Profile Picture

Nayyar Siddiqi 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans