In the plant where Axapta is used, there are 2 shifts - 1st, 2nd
We are trying to schedule people who assemble equipment. An
assembly operation usually takes more hours than can be accomplished
in a single shift. Therefore, people on the next shift take over
and continue assembling the equipment.
I have a single work center group set up that contains all available work centers.
The work centers are of type 'Human Resource' and
represent each of the assembly people. I also have 2 calendars
set up - one for each shift. The work centers contain the
appropriate calendar for the shift the person works.
Whenever I run job scheduling for the production order it always
uses a single work center and schedules it out for multiple
consecutive days, scheduling only one shift per day. I want it to
schedule both shifts in a single day - the first shift work
center, then the second shift work center.
After a single day of both shifts having been
scheduled, then it should begin the process again for the next day
until all of the demand is satisfied.
Any ideas?