Not posting journals cannot be consumed on project budget

(0) ShareShare
ReportReport
Posted on by

Hi all

I created budget of expense category on project and the amount is 100. Then I create expense journal with amount of 80, and I saved this journal there but no post it. Then I created the second expense journal with amount  50, but there is no error pop up. So how to control it even it I didn't post the first journal, it will be consumed from the project budget and the remain budget is 20?

Thank you!

*This post is locked for comments

I have the same question (0)
  • Verified answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hi,

    The project budget will be reduced with the posting of the expense journal. That is, if you have not posted the $80, the budget remains at $100.

    A workaround is the use of the budgeting module where you can also include unposted journals in the budget control.

    Best regards,

    Ludwig

  • Suggested answer
    David Massey Profile Picture
    Microsoft Employee on at

    It should also be noted that one of the two journals will fail to post with a budget overrun error. Which one depends on the order of posting. This assumes you a not allowing overrun in the budget control.

  • Community Member Profile Picture
    on at

    Hi Ludwig

    So can you  share the workaround how to include unposted journals in the budget control?

    Thank you!

  • Verified answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hello Jane.Gu,

    To my knowledge this requires the use of the budget control functionality that is available in the budgeting module.

    Here are some screenprints

    3377.proj2.png

    3377.proj2.png

    To get this work in relation to projects there might be a change necessary in the way how you currently budget.

    That is, the budget control configuration in the budgeting module only checks your project budgets that you have registered in the budgeting module if those budgets are transferred to the ledger budget. There is a specific transfer process available for that at the project level.

    Once the transfer is made and the budget module budget register entries are updated (posted) you can have a budget check on unposted journals.

    Before trying to use this budget module budget control configuration I would recommend that you do some comprehensive testing as this budget control feature requires additional working steps.

    Best regards,

    Ludwig

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Congratulations to our 2025 Community Spotlights

Thanks to all of our 2025 Community Spotlight stars!

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Joris dG Profile Picture

Joris dG 5

#2
Alexey Lekanov Profile Picture

Alexey Lekanov 2

#2
Henrik Nordlöf Profile Picture

Henrik Nordlöf 2 User Group Leader

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans