Dear Colleagues
When I create a route with multiple operations I cannot get a right schedule. In schedule I got different time consumption. THe operation time is 30 minutes but the end date is schedule is 16 days from the start date. How can fix that?
Thanks!
*This post is locked for comments
HI Anna,
I do think that the Gantt Chart is only using a start and end date for the complete process, but not individual days/hours.
Your post is tagged Ax 2009!
Evert Bos -(Sikich) posted an article on D365 Gantt set up recently check his blog posts.-
I read this page, its for DAX2012
In DAX 365 I found this setup form in the menu form Gantt Chart - Content - I selected "Load calendar" check-box, but dont find "Non work interval" check-box.
Where can I find this setings in DAX365?
docs.microsoft.com/.../gantt-chart-setup-form
Have you configured the form e.g.to load calendar, or for the Non-work interval to show as a thin line rather than as a solid bar?
Scheduling direction is "Forward from today".
in form Capacity reservation all is ok, I see 3 date interval.
But in Gantt the line is not interrupted(
Did you set the planning forwards from start date or backwards from the end date? Possibly you can share some details on what you have setup.
Hi!
I have the same problem(
In the route I even created one operation for worker. My worker resourse have a calendar - a day of work then a day off and so on.
After schedule jobs - start date and the end date automatically calculated
In the Gantt schedule I also don t see time work and day off -only continuously line