route and operations

(1) ShareShare
ReportReport
Posted on by Microsoft Employee

Dear Colleagues

When I create a route with multiple operations I cannot get a right schedule. In schedule I got different time consumption. THe operation time is 30 minutes but the end date is schedule is 16 days from the start date. How can fix that?

Thanks!

*This post is locked for comments

  • André Arnaud de Calavon Profile Picture
    André Arnaud de Cal... 291,965 Super User 2025 Season 1 on at
    RE: route and operations

    HI Anna,

    I do think that the Gantt Chart is only using a start and end date for the complete process, but not individual days/hours.

  • Suggested answer
    guk1964 Profile Picture
    guk1964 10,877 on at
    RE: route and operations

    Your post is tagged Ax 2009!

    Evert Bos -(Sikich) posted an article on D365 Gantt set up  recently check his blog posts.-  

  • aevgrafova Profile Picture
    aevgrafova 100 on at
    RE: route and operations

    I read this page, its for DAX2012

    In DAX 365 I found this setup form in the menu form Gantt Chart  - Content - I selected "Load calendar" check-box, but dont find "Non work interval" check-box.

    Where can I find this setings in DAX365?

  • Suggested answer
    guk1964 Profile Picture
    guk1964 10,877 on at
    RE: route and operations

    docs.microsoft.com/.../gantt-chart-setup-form

    Have you configured the form e.g.to load calendar, or for the Non-work interval to show as a thin line rather than as a solid bar?

  • aevgrafova Profile Picture
    aevgrafova 100 on at
    RE: route and operations

    Scheduling direction is "Forward from today".

    in form Capacity reservation all is ok, I see 3 date interval.

    But in Gantt the line is not interrupted(

  • André Arnaud de Calavon Profile Picture
    André Arnaud de Cal... 291,965 Super User 2025 Season 1 on at
    RE: route and operations

    Did you set the planning forwards from start date or backwards from the end date? Possibly you can share some details on what you have setup.

  • aevgrafova Profile Picture
    aevgrafova 100 on at
    RE: route and operations

    Hi!

    I have the same problem(

    In the route I even created one operation for worker. My worker resourse have a calendar - a day of work then a day off and so on.

    After schedule jobs - start date and the end date automatically calculated

    In the Gantt schedule I also don t see time work and day off -only  continuously line

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Announcing Our 2025 Season 1 Super Users!

A new season of Super Users has arrived, and we are so grateful for the daily…

Announcing Forum Attachment Improvements!

We're excited to announce that attachments for replies in forums and improved…

Vahid Ghafarpour – Community Spotlight

We are excited to recognize Vahid Ghafarpour as our February 2025 Community…

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 291,965 Super User 2025 Season 1

#2
Martin Dráb Profile Picture

Martin Dráb 230,817 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans