Microsoft Dynamics AX (Archived)

route and operations

(1) ShareShare
ReportReport
Posted on by

Dear Colleagues

When I create a route with multiple operations I cannot get a right schedule. In schedule I got different time consumption. THe operation time is 30 minutes but the end date is schedule is 16 days from the start date. How can fix that?

Thanks!

*This post is locked for comments

I have the same question (0)
  • aevgrafova Profile Picture
    100 on at

    Hi!

    I have the same problem(

    In the route I even created one operation for worker. My worker resourse have a calendar - a day of work then a day off and so on.

    After schedule jobs - start date and the end date automatically calculated

    In the Gantt schedule I also don t see time work and day off -only  continuously line

  • André Arnaud de Calavon Profile Picture
    300,928 Super User 2025 Season 2 on at

    Did you set the planning forwards from start date or backwards from the end date? Possibly you can share some details on what you have setup.

  • aevgrafova Profile Picture
    100 on at

    Scheduling direction is "Forward from today".

    in form Capacity reservation all is ok, I see 3 date interval.

    But in Gantt the line is not interrupted(

  • Suggested answer
    guk1964 Profile Picture
    10,888 on at

    docs.microsoft.com/.../gantt-chart-setup-form

    Have you configured the form e.g.to load calendar, or for the Non-work interval to show as a thin line rather than as a solid bar?

  • aevgrafova Profile Picture
    100 on at

    I read this page, its for DAX2012

    In DAX 365 I found this setup form in the menu form Gantt Chart  - Content - I selected "Load calendar" check-box, but dont find "Non work interval" check-box.

    Where can I find this setings in DAX365?

  • Suggested answer
    guk1964 Profile Picture
    10,888 on at

    Your post is tagged Ax 2009!

    Evert Bos -(Sikich) posted an article on D365 Gantt set up  recently check his blog posts.-  

  • André Arnaud de Calavon Profile Picture
    300,928 Super User 2025 Season 2 on at

    HI Anna,

    I do think that the Gantt Chart is only using a start and end date for the complete process, but not individual days/hours.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Priya_K Profile Picture

Priya_K 4

#1
Martin Dráb Profile Picture

Martin Dráb 4 Most Valuable Professional

#3
Scott_itD Profile Picture

Scott_itD 2 Community Manager

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans