Hello,
I am seeking advice on the correct process of closing a purchase order for which I originally requested a qty of 10 of a certain item but received 7. I assumed that there would be some sort of audit for this common process which, logically, would allow me to receive and post a purchase invoice for the 7 and mark the purchase order as 'do not expect the remaining qty', close it and allow a discrepancy report to be generated for my supplier evaluation.
The only thing I am see that I am able to do, is manually change the original qty on the PO, which is not very good as a process.