Hello All,

I have one sales order with three line with three item Acid, Alkyne, Liquid .

Now I need to create the work order basis of combination Acid, Liquid or Alkyne ,Liquid. Because as per requirement never Acid and Alkyne will together.

Could you please help me to achieve this scenario.  

Thank you so much for your help !!!!!!!

Regards

Deepak

*This post is locked for comments

I have the same question (0)
  • Crispin John Augustine Profile Picture
    37,081 on at

    How about creating separate works for each Item Group/Type (acid/alkaline/liquid), in that case?

  • Deepak kumar roy Profile Picture
    265 on at

    Thanks so much for reply !!

    We can not use both option because they want to use whole pallet where they want to put one acid/alkyne and liquid.

    Pallet is like a box there they are putting the item after rapping they are sending to customer.

    If we are using the single item once then in pallet space is still available also they need three pallet for each item.

    Regards

    Deepak

  • Verified answer
    Guy Terry Profile Picture
    28,972 Moderator on at

    Can we ask the pickers to pick items in the order Acid -> Liquid -> Alkyne, or Alkyne -> Liquid -> Acid?

    If yes, you could configure the pick snake (Location sort code, and sorting on the Work template) to send the pickers to locations in that order. Then you could use 'Full' when a box is full, or when a box contains Acid & Liquid and there is only Alkyne left to pick.

    'Full' is enabled by ticking 'Allow splitting of work' on the mobile device menu item.

  • Deepak kumar roy Profile Picture
    265 on at

    Hello Terry,

    Thank you so  much for your reply !!!

    As per my requirement i need to create the separate work also so he can assign the some different worker.

    Regards

    Deepak

  • Guy Terry Profile Picture
    28,972 Moderator on at

    If AX should create separate Work automatically, what is the rule that you want it to use to break that work? I mean, without worrying about what AX can or can't do, tell me a rule that describes how the requirement says the work should be split.

  • Deepak kumar roy Profile Picture
    265 on at

    Thanks so much for reply !!!!

    we have used approach that u have suggested and  try to define some more rule.

    Regards

    Deepak

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Meet the Microsoft Dynamics 365 Contact Center Champions

We are thrilled to have these Champions in our Community!

Congratulations to the March Top 10 Community Leaders

These are the community rock stars!

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
CP04-islander Profile Picture

CP04-islander 26

#2