Indirect costs of phantom item not included in cost price of manufactured item

(0) ShareShare
ReportReport
Posted on by

Hello,

I have a phantom item in a Formula (BOM), and indirect costs have been defined in the costing sheet and linked to this phantom item.

Cost price calculation of the phantom item is OK, and shows the indirect costs as expected.

When we calculate the cost price of the manufactured item - with the phantom item included in the Formula (BOM) lines - the indirect costs are not included.

Anyone who knows why they are not included?

Regards,

Bart

*This post is locked for comments

I have the same question (0)
  • Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hello Bart,

    Have you already checked the available hotfixes on LCS to ensure that this system behavior is not caused by a bug?

    Ludwig

  • Suggested answer
    Fredrik Sætre Profile Picture
    12,644 on at

    Interesting... There is a bit of a disconnect here.

    The reason why it is not added is because at estimating a production order, the phantom BOM is exploded and the prodcalctrans has no reference to the phantom item. Changing that would be a major design change/fix.

    The cost calculation does include the phantom item however... If there is a fix, it probably would exclude the phantom items' indirect cost elements.

    You need to move the indirect cost to somewhere else or include a cost carrying item or service in your phantom BOM.

  • Community Member Profile Picture
    on at

    Hello Ludwig, I haven't checked LCS yet. Thanks for the tip.

  • Community Member Profile Picture
    on at

    Hello Fredrik,

    I've been thinking about adding a service item, but in AX2012 it is only possible to add products with an Item Model Group where stocked product is 'checked'.

    A bit of a conflict with a service item & stocked product :-), but yes this is an option.

    Another possibility is to use a planned cost with Explosion mode set to Multilevel (or Make to Order) as this works as I want. And then I just need a simple copy functionality to copy the planned cost to the standard cost.

    Gr, Bart

  • Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hello BartDerhore,

    Please also have a look at Frederiks remark as AX might behave different from what you expect. This is something you should verify in addition.

    Best regards,

    Ludwig

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Congratulations to our 2025 Community Spotlights

Thanks to all of our 2025 Community Spotlight stars!

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Joris dG Profile Picture

Joris dG 5

#2
Sagar Suman Profile Picture

Sagar Suman 2 Super User 2026 Season 1

#2
Alexey Lekanov Profile Picture

Alexey Lekanov 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans