How to handle a subcontract in Project Management and Accounting

(0) ShareShare
ReportReport
Posted on by 200

Hi Folks,

I have created  separate WBS called Subcontract where I need to give this activities outside. Therefore, I have created "Project Category with expense type"  as  Subcontract and tagged with the WBS.

I do not want to book as Direct Expense Journal without placing a PO. Do I need to create a again procurement category? Please let me know how to handle this business  scenarios. Please clarify me the GL accounting also.

pastedimage1643388082862v1.png

Thanks

I have the same question (0)
  • huijij Profile Picture
    19,813 on at

    Hi Senthil,

    Have you get your solution yet?

  • sk.patchai Profile Picture
    200 on at

    No, not yet.

  • Kerry Evans Profile Picture
    167 on at

    To ensure that subcontract activities are not booked as direct expense journals without a purchase order, you can set up a procurement category specifically for subcontracting. This category can be associated with the subcontracting project category and expense type, and configured to require a purchase order before any expenses can be booked against it.

    To set this up, you can follow these steps:

    Create a new procurement category specifically for subcontracting expenses.

    Associate the new procurement category with the subcontracting project category and expense type.

    Configure the procurement category to require a purchase order before expenses can be booked against it.

    When creating purchase orders for subcontracting expenses, be sure to associate them with the correct project and WBS code to ensure that the expenses are booked against the correct project.

    Regarding the GL accounting, you will need to set up appropriate accounting codes for the subcontracting procurement category, as well as for the project and WBS code. These codes should be associated with the appropriate general ledger accounts to ensure that expenses are correctly recorded in the financial statements.

    Overall, by setting up a procurement category specifically for subcontracting expenses and requiring purchase orders, you can ensure that these expenses are properly controlled and tracked in your project accounting system. Additionally, by setting up appropriate GL accounting codes, you can ensure that the financial impact of these expenses is accurately reflected in your financial statements.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Meet the Microsoft Dynamics 365 Contact Center Champions

We are thrilled to have these Champions in our Community!

Congratulations to the April Top 10 Community Leaders

These are the community rock stars!

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Giorgio Bonacorsi Profile Picture

Giorgio Bonacorsi 660

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 655 Super User 2026 Season 1

#3
CP04-islander Profile Picture

CP04-islander 557

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans