Hi all,
In the case of a BOM (material A) containing material lines (material B) of the "phantom" type, the MRP run does not plan the planned production orders for the phantom line (B) on the same requirements date as the leading material (A). The consequence is that the supplies required for the "phantom" BOM (B) are not planned on the requirement date of (A).
Is this a bug ? or a setting