Microsoft Dynamics AX (Archived)

BOM Calculation error

(0) ShareShare
ReportReport
Posted on by

I am getting error: "The route for operation number 80 does not end in zero."

What could be the reason?

*This post is locked for comments

I have the same question (0)
  • Suggested answer
    Nitin Bagate Profile Picture
    77 on at
    RE: BOM Calculation error

    It may be the routes of phantom items. System does some calculation while adding phantom items route to its parent.

    I suspect that you should check routes of all phantom items as those are active and approved.

    Secondly also check the value present in 'Run time' field of each operations. Make sure that no operation has run time value equal to Zero. If any operation in any route has value equal to zero in run time, then such types of warning appears.

    To validate the removal of this error, just run a item cost for parent item. If it ran or able to calculate cost then we are through.

    Best of luck.

    Please post the feedback after you try this.

  • GCW Profile Picture
    80 on at
    RE: BOM Calculation error

    Did you resolve this? I have same issue occuring

  • Weaveriski Profile Picture
    23,616 Moderator on at
    RE: BOM Calculation error

    I presume if you remove the routes from the phantom item it works - what are those routes giving you bearing in mind it is exploding - you only seem to have 10 and 20?

  • Community Member Profile Picture
    on at
    RE: BOM Calculation error

    It definitely relates to phantom items that are used o produce the item.

    Rout number with operation 80 does not really exist.

    It calculates it automatically in BOMCalcTrans.updateReNumberOprNum when it extends phantom items. The error message also comes from the method above.

    But I do not have a clue what is going on during this calculation when it's preparing mapOprNum and then it actually verifies Next number.

    Does somebody knows the business logic behind this code or a possible place where something went wrong?

  • Community Member Profile Picture
    on at
    RE: BOM Calculation error

    Strange, but no.

    It contains same operations

    10 - 20

    20 - 0

  • Marc Claasen Profile Picture
    on at
    RE: BOM Calculation error

    Vasily, please also check the route for the second version in your screen shot. Does that contain an operation 80?

  • Community Member Profile Picture
    on at
    RE: BOM Calculation error

    Operation 10 has Next field 20

    Operation 20 has Next field 0

    You can see that on screenshot

  • Suggested answer
    Marc Claasen Profile Picture
    on at
    RE: BOM Calculation error

    Look at operation 10 and 20 and check the field next (in the line).

    You will see that for both lines the value is not 0.

    So there is no end-operation for AX (there should always be at least one operation with the value of 0 in the field next).

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Abhilash Warrier – Community Spotlight

We are honored to recognize Abhilash Warrier as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Nayyar Siddiqi Profile Picture

Nayyar Siddiqi 2

#1
Martin Dráb Profile Picture

Martin Dráb 2 Most Valuable Professional

#1
Guy Terry Profile Picture

Guy Terry 2 Moderator

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans