Dear experts,
Can someone explain the purpose of Project allocation keys and how it is used?
Path: Project management and accounting > Setup > Forecasts > Project allocation keys.
Thank in advance,
Best regards,
Thu
Hi partner,
Have you read Ludwig's Blog:
dynamicsax-fico.com/.../
Hello ThuNgo,
Project allocation keys are used to allocate or distribute amount defined in project forecast defined for expense, item and fee. For hours, this option is not available.
When you create an expense or fee forecast from a project, you can select the method to allocate amount introduced in the line:
If you select Key option, you will able to select one of allocation keys that you have created like 20 in my example. Then the system will distribute accordingly percentages and periods that you have setup this period key:
For item forecast, the purpose is the same. The difference is the way to allocate amounts. For that you will have to click on Allocate forecast to defined allocation method and the key:
Hope this answer your question.
Regards,
Natalia F Leal
Hi Natalia F Leal,
I think the Project allocation key is selected here
But after selected the key, i find no different. Could you advice where can i find the result?
Hi ThuNgo!
I confirm you that the allocation key used for Key method is one selected in Period key. When you select Period method, you will define periods to distribute proportionally forecast amounts in fields 'Quantity', 'Unit' and 'End date'
But you are right 'Period key' is not the field that you are asking but 'Project allocation key'
I have researched this field further and it seems to be used in expense forecast by forecast reduction feature and not for allocating forecast amounts. Here you can find more details: Project allocation keys (form) | Microsoft Docs
Forecast model can be reduced automatically with amounts used in actuals:
and you can define a lump sum project allocation key for expense in Project management and accounting parameters that will be compared with one set in field project allocation key into expense forecasts:
Lump sum allocation key is mentioned in PMA parameters help: Project management and accounting parameters (form) | Microsoft Docs
Note that similar functionality exists for item forecast but by using item allocation key.
Hope this can help you.
Under review
Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.
As AI tools become more common, we’re introducing a Responsible AI Use…
We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…
These are the community rock stars!
Stay up to date on forum activity by subscribing.
Martin Dráb 503 Most Valuable Professional
André Arnaud de Cal... 434 Super User 2025 Season 2
BillurSamdancioglu 278 Most Valuable Professional