Job WIP reversal and calculate wip costs

(0) ShareShare
ReportReport
Posted on by

We are using the completed contract WIP Method in Company A and the Cost Value WIP Method in Company B

We are now getting transactions for future dates if we have costs post in the next period.  Is it safe to say, that when posting WIP, we should add a Posting date filter like 2/01/2022..2/28/2022 in order to only get costs in the period that we want,

Also, Does WIP in Business Central,  Not reverse itself after it posts the WIP transaction?  I am used to seeing a DR transaction to SIP on 2/28 and a CR on 3/1 for the same WIP amount.  This was never confirmed in Testing and now we are live and have an issue

I have the same question (0)
  • Suggested answer
    Dallefeld Profile Picture
    211 User Group Leader on at

    1. I would limit transactions of costs to be included but rather than 020122..022822, I would enter ..022822, this will get all transactions up to 2/28 but not pickup anything after 2/28.

    2. Job WIP is not just an accrual, depending upon setup Job WIP is recognizing revenue and expense, deferring revenue and expense. Therefore, it does not reverse.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Small and medium business | Business Central, NAV, RMS

#1
OussamaSabbouh Profile Picture

OussamaSabbouh 2,135

#2
YUN ZHU Profile Picture

YUN ZHU 733 Super User 2025 Season 2

#3
Sumit Singh Profile Picture

Sumit Singh 612

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans