HI
i know this has been commented over here already - but...
after changing the "maximum job lead time" to 120 (instead of previous default set 100) in Default Parameters,
on certain job i am stil receiving the error log (after static nrq of a BOM) caliming the job exceeds maximum job LT of 100 days.
Worth noticing is the fact this happens to only one of our products, the reast of production runs smooth.
The error is not present when product forecast has been deleted. Dynamic nrq runs without any problems.
We have checked the Route & could not find any process running over 100 days, especially in Oper. no. 10.
Is there any other option or we need to look further into the BOM & locate the data causing some orocess to run over 100 days ?