Production floor execution

Posted on by 15
I want to use production floor execution without using time and attendance 
How can I do that? 
  • KE-16072243-0 Profile Picture
    KE-16072243-0 15 on at
    Production floor execution
    Thank you ColbyGallagher , that what I was afraid of

    Thank you Andre Arnaud de Cal... 
    To answer your question why do I need to run production floor execution without using time and attendance:
    I want to use production floor execution to:

    schedule jobs, and use these jobs on master planning, and view progress, and view capacity and progress on Gantt chart.

    What I don't want to do is before ending the production order I have to : enter absence, clock out workers, fix lines errors then calculate, approve transfer for every worker, spending time in a task that has zero value for our organization
  • Suggested answer
    ColbyGallagher Profile Picture
    ColbyGallagher 3,664 on at
    Production floor execution
    This is not currently possible, but may be allowed in a future release from what I have heard.  Its a pretty common request.  
  • André Arnaud de Calavon Profile Picture
    André Arnaud de Cal... 291,240 Super User 2024 Season 2 on at
    Production floor execution
    Hi,
     
    Can you explain how your envisioned process should work in the application? In case you don't want to use the specific features, can't you then just use the production journals?
  • KE-16072243-0 Profile Picture
    KE-16072243-0 15 on at
    Production floor execution
    Thanks Kevin Xia 
     
    But I don't need any of that 
    * I don't need clock in/out
    *  I don't need job to submit records to the time registries 
    * I don't need to fix the time registries errors, absence reason, etc
    Actually I don't want to use time &attendance at all

    Oll what I want is production floor execution without time and attendance kick-in 
     
  • Suggested answer
    Kevin Xia Profile Picture
    Kevin Xia Microsoft Employee on at
    Production floor execution
    Hi,
    You can refer to this official document: Configure the production floor execution interface - Supply Chain Management | Dynamics 365 | Microsoft LearnWhen you open the production floor execution interface, it automatically loads a selected configuration and job filter that are specific to the browser and device. In the configuration, you set the policies that must be applicable for a specific usage. Here are some usage examples:
    • On a device in the company hall, employees clock in when they come into the office, and they clock out when they leave for the day.
    • On a device on the shop floor, machine operators register when they start and complete jobs. They also register breaks and indirect activities.
    You can check whether you can cancel related settings.
    Best regards,
    Kevin

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

December Spotlight Star - Muhammad Affan

Congratulations to a top community star!

Top 10 leaders for November!

Congratulations to our November super stars!

Community AMA December 12th

Join us as we continue to demystify the Dynamics 365 Contact Center

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 291,240 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 230,149 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans