When assigning duration and effort to a resource, the system tries to split this effort out over the duration e.g.:
This can cause some issues when trying to convert a Generic resource into a named.
The system will try to book 99,97 hours and hereby not fulfill the Resource requirement -> The named resource will not be displayed in the task-list..
How do you guys deal with these fraction decimals that are quite annoying.
Thanks!

Report
All responses (
Answers (