Hello,
I need your advice for the configuration of the routes and that the production planning runs well.
Scenario:
- I have a route with 5 operations, three for cut and two for assembly
- Cut process has only one resource group with 2 work centers
- Assembly have two resource groups (production line) with two work centers each, this resource groups have the same function and capabilities, the variable for assignment is the workload.
How can I configure the route for the planning use only resource group for assembly and don´t combine workcenters for the assembly resources groups?... I need to use job schedulling.
Regards,