Error: Budget Exceed for Project

(0) ShareShare
ReportReport
Posted on by 19
Error 'The entry category for 40200 on project 4000842-001 cannot be submitted because it would cause the cost budget to be exceeded by 62.17' is seen when attempting to confirm or invoice purchase order, which is tied to a project. Project balance is sufficient.
 
This issue happened after a purchase order line was amended.
 
Checks indicate few of the purchase order line are not defined in the budget. Only one PO line is defined (meaning it has an activity number tied to the project, and has budget period).
 
 
Due to urgent request to have this PO invoiced, budget overrun is allowed.
Would appreciate help with correcting this error without allowing budget overrun.
I have the same question (0)
  • Judy Profile Picture
    Microsoft Employee on at
    Error: Budget Exceed for Project
    Hi,
     
    Can you confirm if the issue is due to some extensions or third-parties.
    You can submit a SR to Microsoft for further investigation.
     
     
    Best Regards,
    Judy
  • Torlila Profile Picture
    19 on at
    Error: Budget Exceed for Project
    Hi Judy,
     
    There is no extension or third party involved.
  • Suggested answer
    saurabh bharti Profile Picture
    15,039 Moderator on at
    Error: Budget Exceed for Project
    Hi,
     
    Looks like you have project budget defined for this category and activity combination and also validation of budget on project master data.
     
    This is showing exceeding the budget by 62.15 , and on project budget remianing budget is zero.
     
    Can you go to project and check if the budget is approved? 
     
     
  • Torlila Profile Picture
    19 on at
    Error: Budget Exceed for Project
    Hi saurabh bharti,
     
    Yes, there is project budget defined for this category and activity. There is sufficient budget.
    However, checking through each PO line financials, I notice there is another category for three of the PO lines, which does not have an activity assigned to it. Nor does it have a period year, and budget is not defined.
    Refer screenshots below.
     
    PO line financials showing one PID category has activity and budget period defined, the other does not have activity and budget defined.
     
     
    I believe this is the issue.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Abhilash Warrier – Community Spotlight

We are honored to recognize Abhilash Warrier as our Community Spotlight honoree for…

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
CA Neeraj Kumar Profile Picture

CA Neeraj Kumar 813

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 738 Super User 2025 Season 2

#3
Sohaib Cheema Profile Picture

Sohaib Cheema 566 User Group Leader

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans