Does Project Operations support sub-projects out of the box on the CE side to be synced over to F&O?
Thanks
Michael
Hi Michael. ProjOps Lite/Integrated doesn't support sub-projects the way F&O only does. In Lite/Integrated, you can create multiple Order Lines on your Project Contract and map a different project to each Order Line. In the April 2021 update for Integrated (Project Operations on Dataverse environment version 4.9.0.221 / Project management and accounting in Dynamics 365 Finance environment version 10.0.17) you can also use Task Based Billing:
docs.microsoft.com/.../whats-new-apr-2021-resource-based
Hi Antti,
Thanks for your answer. Do you know if sub-project support on the CE side is on the roadmap, if that's the case, when will it be released?
Kind Regards
Nothing official planned. Wouldn't hold my breath.
Under review
Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.
Congratulations to our 2026 Super Stars!
Thanks to all of our 2025 Community Spotlight stars!
These are the community rock stars!
Stay up to date on forum activity by subscribing.
André Arnaud de Cal... 590 Super User 2026 Season 1
Giorgio Bonacorsi 349
Diego Mancassola 263