Project timesheet workflow, what type of auto approval condition is required to auto approve timesheet after 1 day.

(0) ShareShare
ReportReport
Posted on by 815

Hi,

Ax2012 R3.

We are running AX 2012 R3 and  using project timesheet workflow and it is running fine.

We want to add a auto approval condition in workflow to auto approve the timesheet after 1 day.

What kind of condition is required to achieve the above requirement?

Thanks in advance.

4300.screenshot.jpg

Regards,
Nadeem

*This post is locked for comments

I have the same question (0)
  • Verified answer
    Sohaib Cheema Profile Picture
    49,677 Super User 2026 Season 1 on at

    go inside the approval step and configure auto-approval using escalation.

    this will not escalate workflow anywhere but will auto approve.

  • Nadeem Profile Picture
    815 on at

    Hi Sohaib,

    Thanks for providing the link. I will add this and test to confirm.

  • Nadeem Profile Picture
    815 on at

    Hi Sohaib,

    I have tried this by adding the limit to 1 hour and then set the escalation to 1 hour.

    I can see the workItemCreated and below details.

    "Assigned to user: Due date 18/01/2016 12:39" which is exactly one hour after I submitted the timesheet but time sheet did not get approved after 1:30 minutes passed.

    any ideas why it  didn't work?

    thanks in advance.

    Regards,

    Nadeem

  • Sohaib Cheema Profile Picture
    49,677 Super User 2026 Season 1 on at

    I am unable to understand what you said in your recent reply. kindly try to elaborate your case.

  • Nadeem Profile Picture
    815 on at

    apologies, I repeated some of the test. I have tried the escalation option for 1 hour and it did not work in first instance. I have tried it second time and it has worked.

    I will carry out one more test and come back.

    Regards,

  • Nadeem Profile Picture
    815 on at

    Hi Sohaib,

    Escalation is actually working but approval happens close to 2 hours or some time around 1 hour 30 minutes which could be due to "Workflow due date process" batch job running after every one hour.

    I have changed the recurrence for this batch job to 10 minutes to see whether escalation will happen closer to  one hour, otherwise setting it to 2 minutes will give the desired result.

    I will test this scenario now.

  • Sohaib Cheema Profile Picture
    49,677 Super User 2026 Season 1 on at

    yeah that is something related to Batch processing. The duty of workflow framework is finished after giving tasks/workitems to BATCH job.

  • Verified answer
    Nadeem Profile Picture
    815 on at

    Working accordingly now.

    Resolution:

    1- Use workflow escalation feature.

    2- setup recurrence for batch job "Workflow due date process" accordingly.

    Thanks Sohaib.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Meet the Microsoft Dynamics 365 Contact Center Champions

We are thrilled to have these Champions in our Community!

Congratulations to the March Top 10 Community Leaders

These are the community rock stars!

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Joris dG Profile Picture

Joris dG 5

#2
Andrew Jones a1x Profile Picture

Andrew Jones a1x 2

#3
GL-01081504-0 Profile Picture

GL-01081504-0 1

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans