Announcements
No record found.
Hi,
Is there a way to change the behavior of the task dependencies in project operations to support the following use case:
The question is: If Task 1 is moved to start date 2021-04-10 I would like the child tasks to be moved accordingly. The desired result should be:
Thanks
Michael
Dowert what you're describing is how the task dates do change when dependencies are created. With those specific dates you have a Saturday on the 10th and a Sunday on the 11th. Make sure your calendar template supports weekends as working days.
Hi Antti, thanks for the answer. I understand that the task is moved to the next working day, but the sub tasks are not following along.
Here is a picture of the original planning:
Here is a picture when I have changed the start date of Lesson 1 to the 12th of April. I would like to have the sub tasks to be moved accordingly, Lesson 2 on the 13th and Lesson 3 on the 14th.
Is this feasible?
Kind Regards
Calendars for the project and resources are still the only things I can think of. When I change tasks, the dependent tasks move forward. Both with and without assignments.
Before change.
After change.
Hi Antti,
Thanks for you fast reply. Unfortunately, it still doesn’t fulfil the requirements I have.
Under review
Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.
Congratulations to our 2026 Super Stars!
Thanks to all of our 2025 Community Spotlight stars!
These are the community rock stars!
Stay up to date on forum activity by subscribing.
André Arnaud de Cal... 512 Super User 2026 Season 1
Giorgio Bonacorsi 386
Adis 259 Super User 2026 Season 1