Skip to main content

Notifications

Announcements

No record found.

Community site session details

Community site session details

Session Id :
Finance | Project Operations, Human Resources, ...
Suggested answer

Task Dependencies Behavior

(1) ShareShare
ReportReport
Posted on by 25

Hi,

Is there a way to change the behavior of the task dependencies in project operations to support the following use case:

  • Task 1, duration 8h, start 2021-04-07, finish 2021-04-07
    • Task 2, duration 8h, start 2021-04-08, finish 2021-04-08, dependent on Task 1
      • Task 3, duration 8h, start 2021-04-09, finish 2021-04-09, dependent on Task 2

The question is: If Task 1 is moved to start date 2021-04-10 I would like the child tasks to be moved accordingly. The desired result should be:

  • Task 1, duration 8h, start 2021-04-10finish 2021-04-10
    • Task 2, duration 8h, start 2021-04-11, finish 2021-04-11, dependent on Task 1
      • Task 3, duration 8h, start 2021-04-12, finish 2021-04-12, dependent on Task 2

Thanks

Michael

  • Zodix Profile Picture
    25 on at
    RE: Task Dependencies Behavior

    Hi Antti,

    Thanks for you fast reply. Unfortunately, it still doesn’t fulfil the requirements I have.

    Michael

  • apa Profile Picture
    8,284 Moderator on at
    RE: Task Dependencies Behavior

    Calendars for the project and resources are still the only things I can think of. When I change tasks, the dependent tasks move forward. Both with and without assignments.

    Before change.

    Tasks-12-to-14.png

    After change.

    Tasks-14-to-16.png

  • Zodix Profile Picture
    25 on at
    RE: Task Dependencies Behavior

    Hi Antti, thanks for the answer. I understand that the task is moved to the next working day, but the sub tasks are not following along.

     

    Here is a picture of the original planning:

    pastedimage1617743024223v2.png

     

    Here is a picture when I have changed the start date of Lesson 1 to the 12th of April. I would like to have the sub tasks to be moved accordingly, Lesson 2 on the 13th and Lesson 3 on the 14th.

     pastedimage1617743012618v1.png

     

    Is this feasible?

     

    Kind Regards

    Michael

  • Suggested answer
    apa Profile Picture
    8,284 Moderator on at
    RE: Task Dependencies Behavior

    Dowert what you're describing is how the task dates do change when dependencies are created. With those specific dates you have a Saturday on the 10th and a Sunday on the 11th. Make sure your calendar template supports weekends as working days.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Daivat Vartak – Community Spotlight

We are honored to recognize Daivat Vartak as our March 2025 Community…

Announcing Our 2025 Season 1 Super Users!

A new season of Super Users has arrived, and we are so grateful for the daily…

Kudos to the February Top 10 Community Stars!

Thanks for all your good work in the Community!

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 293,278 Super User 2025 Season 1

#2
Martin Dráb Profile Picture

Martin Dráb 232,021 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156 Moderator

Leaderboard

Product updates

Dynamics 365 release plans