web
You’re offline. This is a read only version of the page.
close
Skip to main content

Announcements

No record found.

News and Announcements icon
Community site session details

Community site session details

Session Id :
Finance | Project Operations, Human Resources, ...
Suggested Answer

Task Dependencies Behavior

(1) ShareShare
ReportReport
Posted on by 25

Hi,

Is there a way to change the behavior of the task dependencies in project operations to support the following use case:

  • Task 1, duration 8h, start 2021-04-07, finish 2021-04-07
    • Task 2, duration 8h, start 2021-04-08, finish 2021-04-08, dependent on Task 1
      • Task 3, duration 8h, start 2021-04-09, finish 2021-04-09, dependent on Task 2

The question is: If Task 1 is moved to start date 2021-04-10 I would like the child tasks to be moved accordingly. The desired result should be:

  • Task 1, duration 8h, start 2021-04-10finish 2021-04-10
    • Task 2, duration 8h, start 2021-04-11, finish 2021-04-11, dependent on Task 1
      • Task 3, duration 8h, start 2021-04-12, finish 2021-04-12, dependent on Task 2

Thanks

Michael

I have the same question (0)
  • Suggested answer
    apa Profile Picture
    8,284 Moderator on at

    Dowert what you're describing is how the task dates do change when dependencies are created. With those specific dates you have a Saturday on the 10th and a Sunday on the 11th. Make sure your calendar template supports weekends as working days.

  • Zodix Profile Picture
    25 on at

    Hi Antti, thanks for the answer. I understand that the task is moved to the next working day, but the sub tasks are not following along.

     

    Here is a picture of the original planning:

    pastedimage1617743024223v2.png

     

    Here is a picture when I have changed the start date of Lesson 1 to the 12th of April. I would like to have the sub tasks to be moved accordingly, Lesson 2 on the 13th and Lesson 3 on the 14th.

     pastedimage1617743012618v1.png

     

    Is this feasible?

     

    Kind Regards

    Michael

  • apa Profile Picture
    8,284 Moderator on at

    Calendars for the project and resources are still the only things I can think of. When I change tasks, the dependent tasks move forward. Both with and without assignments.

    Before change.

    Tasks-12-to-14.png

    After change.

    Tasks-14-to-16.png

  • Zodix Profile Picture
    25 on at

    Hi Antti,

    Thanks for you fast reply. Unfortunately, it still doesn’t fulfil the requirements I have.

    Michael

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Congratulations to our 2025 Community Spotlights

Thanks to all of our 2025 Community Spotlight stars!

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 512 Super User 2026 Season 1

#2
Giorgio Bonacorsi Profile Picture

Giorgio Bonacorsi 386

#3
Adis Profile Picture

Adis 259 Super User 2026 Season 1

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans