Master planning generates multiple planned purchase orders without grouping

(0) ShareShare
ReportReport
Posted on by 29

Hello everyone,

Master planning is creating 2 planned purchase orders (PPO) for the item without consolidating the total quantity.

First Planned Purchase order (PPO) is for safety stock: refer Image 1

Second Planned Purchase order (PPO) is against a sale order demand: refer Image 2

I noticed that the 1st PPO pegged to safety stock and has the warehouse mentioned as "MK MAIN".

But the 2nd PPO is pegged for Sale order demand and the warehouse is blank and has only site. Any particular reason for this?

On my sale order line for this item, the storage dimensions is updated with Site & Warehouse. So I am assuming the 2nd PPO pegged against sale order should contain warehouse, or is this based on some parameter which I am missing? 

Note: The Item and warehouse are AWMS enabled.

I need your help to understand the above behavior of master planning.

Thanks in Advance.

IMAGE 1:
pastedimage1679337128146v3.png

IMAGE 2:

pastedimage1679337059002v2.png

I have the same question (0)
  • Laurens vd Tang Profile Picture
    4,010 Super User 2025 Season 2 on at

    Hi Karthik,

    Can you a screen shot of the coverage group?

    Regards,

    Laurens

  • Karthik Manavalan Profile Picture
    29 on at

    Hi Laurens,

    Screenshot given below for your reference.

    pastedimage1679339417298v1.png

  • Laurens vd Tang Profile Picture
    4,010 Super User 2025 Season 2 on at

    Hi Karthik,

    Thanks. Is it correct that the requirement date is different per planned order?

    Regards,

    Laurens

  • Karthik Manavalan Profile Picture
    29 on at

    Hi Laurens,

    Yes, the requirement date is different per planned order but with an interval of 10 days. But as per the coverage period set as 30 days in the coverage group, should the master planning combine all the demand for a period of 30 days and create a single planned purchase order?

    For 1st PPO pegged against safety stock the requirement date is 3/20/2023.

    For 2nd PPO pegged against sale order demand the requirement date is 3/29/2023.

    Thanks,

    Karthik.

  • Laurens vd Tang Profile Picture
    4,010 Super User 2025 Season 2 on at

    Hi Karthik,

    I think in case of different requirement days, it means also different delivery dates, what probably means different purchase orders or purchase order lines.

    Regards,

    Laurens

  • Karthik Manavalan Profile Picture
    29 on at

    Hi Laurens,

    Yes, I need both lines in Purchase order to be with same delivery dates.

    But, however master planning has created 2 PPOs with different delivery dates even though coverage period set is 30 days.

    The warehouse field is the difference between 2 PPOs which I suspect as reason, but I am not sure.

    Thanks,

    Karthik.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Supply chain | Supply Chain Management, Commerce

#1
Laurens vd Tang Profile Picture

Laurens vd Tang 302 Super User 2025 Season 2

#2
Siv Sagar Profile Picture

Siv Sagar 183 Super User 2025 Season 2

#3
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 120 Super User 2025 Season 2

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans