When a production order is rescheduled, the system doesn’t automatically adjust the requirement dates for BOM (Bill of Material) items if the production order is already in the Started status. This is a common scenario, as once a production order is in progress, Dynamics 365 treats the planned requirements as "fixed" based on the original schedule. However, there are a few ways to address this without having to roll back the production order.
1. Manually Adjust BOM Item Requirement Dates
This approach can be time-consuming if you have many BOM items, but it’s a straightforward way to get accurate dates.
Sometimes, running an explosion can recalibrate the demand for BOM items, although this may not always update dates if the production order is already started.
Note: Delay Calculation works well if you’re running MRP (Material Requirements Planning) frequently, as it can help to identify and correct requirement dates.
For the immediate situation, your best options are likely:
Unfortunately, Dynamics 365 doesn’t provide an out-of-the-box automated way to reschedule BOM requirements after a production order has started. This behavior is typically controlled to avoid unintended changes to ongoing orders, but the workarounds above should help you manage this without rolling back the production order.
André Arnaud de Cal...
292,468
Super User 2025 Season 1
Martin Dráb
231,287
Most Valuable Professional
nmaenpaa
101,156