Hi
We have MRP run over multiple warehouses. We have a main warehouse X define as supplier delivery warehouse and Z warehouse as production facility. We configure Z as transfer from X
Time comes we need to speed delivery and directly deliver from supplier to production facility. Is there a way to make the change in planned order (in the previsional purchase order). As for now it looks like it is not possible to modify the value :(AL-SAS-01 is the warehouse code from X warehouse)
The only workaround we found is to change the previsional transfer into previsional purchase order. Is the a faster more direct way?