Using D365 Online Project Service Automation with 2020 Wave 1 Enabled, Microsoft Project Professional 2016 Version 1908
I have a Project created in PSA, with project tasks / WBS set up in PSA with UK Date format for start and end dates i.e. dd/mm/yyyy. My user's personal settings are set with this date format, as are the global system settings. In MS Project i also have the exact same date format settings.
When I connect MS Project to Dynamics, and then try to read from existing Project Service project i get the following error: "The date you entered isn't supported for this field."
Some example dates in the PSA tasks include 13th May 2020, which is 13/05/2020 in UK date format.
If i change all dates so that they do not occur beyond the 12th day of the month then the project imports successfully and with the correct dates i.e. the 6th of May formatted as 06/05/2020 imports still as the 6th May 2020 to MS Project rather than as the 5th June.
Any suggestions as to how to resolve this issue?