We had our production orders setup to show as committed cost on our projects. Once the production order is ended, the committed cost is removed and the actual costs posted to the project. We decided to change this so we did not see committed cost with our production orders. When we did this, "in-flight" production orders that had already posted committed cost to our project did not clear the committed cost once it was ended. Now our project has the actual cost and the committed cost.
We need to clear the committed cost but don't know how to do this. We thought about turning it back on but since the prod orders are already ended, there is no mechanism to trigger the removal of the committed cost.
Is there a way to clear committed cost created from a production order after the production order is already ended?