Hi All,
We just started using PSA. When our team members are trying to book their hours with time entry the error ribbon says - "you don't have a resource record associated. Please contact the administrator to create a resource record."
We have followed all of the steps and not sure on what scenario this error pops up ?
1. Created a project.
2. Assigned team member.
3. Used work down break structure to include a task and associate the above team member with certain hours.
SO not sure what exactly are we missing here