In the preview version 10.0.38, when the functionnality Supplier requested and confirmed shipment dates is actived, it is possible to overwritte the calculated date ?
It can happen that the delivery schedule has an exception for a specific order. But as we change the ship date or delivery date it recalculate again the other date :
- Purchase order : The transportation days is 3 days for this adresse
Requested Shipdate : 16 January
Delivery date : 19 January
After contact with the vendor, we manage to organize transport on the 16 of January for the 18 of January.
Confirmed shipdate : 16 of January
Confirmed delivery date : 19 of January
If we change the delivery date to be correct (the 18 of january), the confirmed shipdate would be the 15 of January which is incorrect.
We could create a specific Delivery mode for that case but we will loose the purpose of it ( or we will have to create a delivery mode for each transport type for each days of transport).
Is there a way to overwritte the calculation for specific needs ?
We also noticed that the shipdate in the past is not blocked when set up in the field even though we configure the parameter to do so.