Good day
I am trying to do an estimate and elimination on an Investment Project in AX2012. I have created the WBS and linked Items and hours, I have also posted 2x POs for the project - both POs are Approved status = Finalised and Status = Invoiced.
On creation of the estimate, I allow sufficient time on the Estimate date, but the Percentage complete remains = 0,00. When I check under Control>Payment retained from vendors>By PO, I see the two POs there. I assume that is the reason?


What setup do I miss or what is the reason for the Elimination percentage issue?
Thanks