Copy a PO (Repeat PO)

(0) ShareShare
ReportReport
Posted on by 128

We are following these steps to create a repeat PO: https://docs.microsoft.com/en-us/dynamics365/supply-chain/procurement/tasks/create-repeat-purchase-order

But when we click okay, we are getting the error below.  Do you know why we are getting the error and how to fix it?  We did not put any project information on the PO before clicking the okay button for the prior into to be copied over. 

pastedimage1661519454535v1.png

I have the same question (0)
  • BillurSamdancioglu Profile Picture
    19,703 Most Valuable Professional on at

    Does the PO that you want to copy has been generated from a project?

  • Ferguson - TD Profile Picture
    128 on at

    Yes, about 90% of our POs are generated from a project.

  • Verified answer
    Moazzma Iqbal Profile Picture
    105 on at

    Hi Jennifer,

    The error shows as a project wasn’t specified while creating a PO. When you create a PO manually through Procurement and Sourcing/Accounts Payable, you will have to specify project after specifying vendor. If you are copying a PO that was created using project, you will have to add the project to PO while creating it. You can refer to the image for adding project to PO. 

    pastedimage1661728015281v1.png

    After that if you copy the PO, you should be able to copy it.

    Let us know if this resolve your issue. 

    Moazzma

  • Ferguson - TD Profile Picture
    128 on at

    Hi, this did get us past the first error but the new PO was created with a different project than I had put on the new PO.

    I created the new PO with project number 00001068-001 but the new PO was created with 00001100-001 but trying to use the same task code for 00001068-001, which is giving us an error (as it should).  

    So, it changed the project number but kept the activity number.  

  • Moazzma Iqbal Profile Picture
    105 on at

    Did it created the PO with Project 00001100-001 when you selected the Project 00001068-001?

    It would be great if you can share a few screenshots for explanation.

  • Ferguson - TD Profile Picture
    128 on at

    I think I figured it out.  If I choose "Copy precisely" it overrides the project number I put on the new PO with the project from the PO I am copying from but the activity number doesn't change.  

    As long as I don't choose copy precisely, the info remained as I expected it to.

    Thank you for your help!

  • Moazzma Iqbal Profile Picture
    105 on at

    Glad to hear that!

    Please, verify any answers that has been helpful in resolving your issue. It will be helpful for other users.

    Thank you.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Neeraj Kumar – Community Spotlight

We are honored to recognize Neeraj Kumar as our Community Spotlight honoree for…

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
Martin Dráb Profile Picture

Martin Dráb 660 Most Valuable Professional

#2
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 549 Super User 2025 Season 2

#3
Sohaib Cheema Profile Picture

Sohaib Cheema 307 User Group Leader

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans