I have a group of 6 machines that CAN run 20 hours each per day (10 hours, 2 shifts).
I have 4 people to run that group of machines (each machine takes 1 person to operate).
Because of the human constraints, we can only load the group of machines to 40 hours. (I have 2 people on 2, 10 hour shifts).
I don't care how many hours go to each machine, I just don't want the group to be loaded over 40 hours. How to I get Axapta set up to think like this?
*This post is locked for comments
I have the same question (0)

Report
All responses (
Answers (