Hi ,
Am facing an issue in Project Management - WBS. Scenario listed below -
- Created a Project with WBS and Published.
- Transferred to Forecast and Budget and Approved.
- Actuals recorded.
- Wanted to add few changes of additional activities with cost estimates. Here is the issue -
- When i edit WBS and Make changes and then publish - am facing the error "Cannot edit a record in Hierarchy tree (HierarchyTreeTable). The record has never been selected..
- Even when i change the published WBS to edit and when i tried republishing without any change, am facing the same issue.
When we checked the table, the line available in projplanversion doesn't have the hierarchytreetablerefrecid for 2 lines. How can this be sorted. I even tried to delete and recreate the line, but system is not allowing the publish as i have actuals recorded against the activity.
Can i get a solution on this? The technical team is not able to fix this.
THanks
Deepa