Hi
I have a question maybe someone has an answer to.
We are using WMS for making transfer Order picking.
It has been nesasary to split the Transfer order (00051) on multible work id, eash Work ID is picking materials for a specifick location ZoneID in the Warehouse
Work ID:*98 = ZoneID A
Work ID:*99 = ZoneID 1
Work ID:*100 = ZoneID 2
Work ID:*101= ZoneID 3
But since the hole transfer order is being released to warehouse at the same time all workiID created is getting the same Work creation ID (000000058) and also being allocated to the same load.
My problem is now that I can’t confirm a shipment for each work ID before all Work lines for the Work creation number and load, has been completed and all the WorkID has status closed.
I would like then when One WorkID is status closed it should be possible to confirm that shipment and ship the trasfer oder.
Do any of you now how to make this setup
Thank you in advance
BR
Jonas
*This post is locked for comments
I have the same question (0)Have you tried putting the transfer order lines (which will be transferred separately) on to separate Loads? You can use the Load planning workbench to Add each transfer order line to new Load. You'll probably also then need to use the Load planning workbench to release each Load to the warehouse.