CTP for planning optimization

Posted on by 139
Is CTP for Planning optimization configured the same way as for CTP for master planning?
Is the recommended control method in this case CTP for Planning optimization for both produced item and its components?
 
Kind regards,
Categories:
  • Suggested answer
    Kevin Xia Profile Picture
    Kevin Xia Microsoft Employee on at
    CTP for planning optimization
    Hi,
    Yes, in this case, the usual recommended control method is the use of plan-optimized CTP for both the production material and its components. By applying CTP at both levels, you can ensure that production planning and component availability are aligned with overall planning goals and constraints.
    Best regards,
    Kevin

Helpful resources

Quick Links

Contextual content recommendations & SharePoint Q&A

Instantly access relevant sales materials…

Beyond the DRA Cloud Label Printing

Explore cloud-based label printing within Dynamics 365…

HR Infrastructure Customer merge

Important considerations for HR Customer migrations…

Leaderboard

#1
Andre Arnaud de Calavon Profile Picture

Andre Arnaud de Cal... 283,418 Super User

#2
Martin Dráb Profile Picture

Martin Dráb 223,631 Super User

#3
nmaenpaa Profile Picture

nmaenpaa 101,142

Featured topics

Product updates

Dynamics 365 release plans