Microsoft Dynamics AX (Archived)

item requirement cost not incurred in project

(0) ShareShare
ReportReport
Posted on by 4,057

Hi All,

I have created the Purchase order from the item requirement and at the time of receiving the PO system giving me message to consume it immediately, i click ok then post the sales packing slip. After that when i go to project to see the cost incurred in the project it shows zero. My item on the PO is Non-stocked item.

Can u tell me the reason why for the non stocked item cost is not incurred in the project and how to fix this issue.

Thanks in advance.

*This post is locked for comments

  • Suggested answer
    RamK Profile Picture
    2,580 on at
  • imran ul haq Profile Picture
    4,057 on at

    Thanks Ram but this blog is not my answer.

    My Item requirement functionality is working fine with the stocked item, it is incurring the cost in the project at the time of product receipt but for the non stocked item it is not incurring at the time of invoicing only.

  • Verified answer
    Weaveriski Profile Picture
    23,620 Moderator on at

    You dont stock a non-stocked item, so the cost can only be incurred at invoice because you never receive it into stock.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Season of Sharing Community Challenge Winners!

Congratulations to our community stars!

Women in Power Builds Momentum

Expanding mentorship, skilling, and AI innovation

Congratulations to the August Top 10 Community Leaders

These are the community rock stars!

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans