Calendar needs to be set for the parent project

(0) ShareShare
ReportReport
Posted on by 1,419

Hi, 

We are in the process of testing the Project management and accounting module. It´s three users using the module, myself and two more. Both of them get a warning message when creating subprojects saying: "Calendar needs to be set for the parent project". This seems to be solved for them when filling in the parent project the field "Scheduling calendar": 

pastedimage1588148482502v1.png

But this does not make sense for two reason: 

* We are not using project scheduling or budgets at all. 

* I am not getting this warning when creating sub projects, so it makes me think that it´s user related. 

Any insights? 

Thank you very much! 

I have the same question (0)
  • Verified answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at

    Hi,

    There is a setting in the project management parameters where you can define a default scheduling calendar that is automatically inserted at the time new projects are created. I would recommend making this setup especially if you are not making use of this functionality and simply want to get rid of this warning.

    Best regards,

    Ludwig

  • Verified answer
    Rahul Mohta Profile Picture
    21,032 on at

    and if calendar varies per project, could then make it mandatory or bring it to the main list page for users to assign and trickle to child projects

  • Verified answer
    NataliaLeal Profile Picture
    Microsoft Employee on at

    Hi Rahul,

    As far as I know the calendar is used in the project hierarchy to validate start dates and end dates for every project and not only for every activity. That is way this is mandatory when creating a subproject and not only subproject format.

    The calendar specified or modfied from the parent project is automatically updated in the subprojects. From subproject, you can specify a different calendar to one in the parent and it will modify calendars in subproject behind this branch.

    Calendars set in resources are used to calculate the capacity of every worker and then it is compared with project planning.

    Hope this answers your question. Let us know if you have any doubt.

    Regards,

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Congratulations to our 2025 Community Spotlights

Thanks to all of our 2025 Community Spotlight stars!

Leaderboard > Finance | Project Operations, Human Resources, AX, GP, SL

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 510 Super User 2026 Season 1

#2
Giorgio Bonacorsi Profile Picture

Giorgio Bonacorsi 399

#3
Adis Profile Picture

Adis 251 Super User 2026 Season 1

Last 30 days Overall leaderboard

Product updates

Dynamics 365 release plans