Microsoft Dynamics AX (Archived)

Minimum stock is not consumed

(0) ShareShare
ReportReport
Posted on by

Hi all,

I use a masterplan with a Min./Max coverage method.

When a sales order need to consume the minimum stock, a planned order is created, even if the physically available stock permit to deliver the order.

I don't understand why, on an other company it works fine but not on this one. I surely missed a setup... ?

*This post is locked for comments

I have the same question (0)
  • Community Member Profile Picture
    on at

    If I uncheck perspective messages, it consume the stock, but it didn't reserved automatically ...

    If my mini is 10 and I need 5 on this minimum stock, it creates a planned order for 5, and didn't reserve automatically the 5 on the minimum stock (but on the planned order). I need it reserve the minimum stock.

  • Weaveriski Profile Picture
    23,620 Moderator on at

    The reservation is related to the sales order, not the planned order. It would reserve against the 5 being taken from stock. Your replenishment order back up to your minimum is not reserved, it is to fulfill the minimum.

    AX does not consume the minimum stock, it is when that number is broken, so if your minimum is 10 you do not need demand for 10, you need demand that takes your on hand to the trigger point.

  • Community Member Profile Picture
    on at

    I'm not sure to understand. The minimum stock can not be consumed the time that I replenishes the product?

    Yes it doesn't reserve on the planned order, but the link between the needs is create with the planned order, and I want it reserve on stock, even if the minimun stock is reached.

  • Community Member Profile Picture
    on at

    Look that,

    162 on-hand physically
    My stock minimun is 52.

    115 sold.
    110 reserved physically, 5 in planned order.
    Why it didn't take the 5 needed on the 52 physically available

    Sans_2D00_titre_2D00_1.jpg

  • Weaveriski Profile Picture
    23,620 Moderator on at

    I cannot understand the details therein relation to the reference. You need to look at the net requirements. It will take the 5 needed from the physical, the planned for 5 would be based upon breaking of the minimum level.

    If the 5 is a sales order then it may depend upon how the requirement has been created depending upon the dimensions where you define item coverage and where the demand actually is - so do you plan by warehouse and is this all at the same warehouse?

  • Verified answer
    Community Member Profile Picture
    on at

    Ok I found how it can done what I expect.

    In the Coverage Item form, I need to select "First Issue" for "Fulfill minimum"

  • Weaveriski Profile Picture
    23,620 Moderator on at

    Ah so the issue is probably you were seeing the planned order created today, with the default "Todays Date" but it should not have impacted on reservations from a planned perspective. Still if you have your answer that is good!!

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Congratulations to our 2025 Community Spotlights

Thanks to all of our 2025 Community Spotlight stars!

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Joris dG Profile Picture

Joris dG 5

#2
Alexey Lekanov Profile Picture

Alexey Lekanov 2

#2
Henrik Nordlöf Profile Picture

Henrik Nordlöf 2 User Group Leader

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans