Committed date in Project accounting

Posted on by 520

Hi,

I created a PO under Project management and accounting>>Common>>Project>>All projects then click manage tab in the action pane>>Item task>>Purchase order.

The PO creation date is July 22 as well as the accounting date and delivery date but when I check the date in Committed cost, the date is July 23.

Why is it that the committed date is July 23 and where that date came from?

Pls enlighten me.

Thanks.

  • Verified answer
    Ludwig Reinhard Profile Picture
    Ludwig Reinhard Microsoft Employee on at
    RE: Committed date in Project accounting

    Good morning marypeace,

    Is there anything else the community can help you in regards to this question?

    If this is not the case and if your question has been answered then please be so kind and verify the answers.

    Many thanks and best regards,

    Ludwig

  • Suggested answer
    Ludwig Reinhard Profile Picture
    Ludwig Reinhard Microsoft Employee on at
    RE: Committed date in Project accounting

    I see.

    In this case, I would suggest that you keep an eye on that and if it happens again then probably open a support request with MS.

    Best regards,

    Ludwig

  • marypeace Profile Picture
    marypeace 520 on at
    RE: Committed date in Project accounting

    Hi Ludwig,

    I created another PO in demo environment and It did not happen again.

    The creation date, accounting date and delivery date are all the same and the committed cost also get the correct date which is the accounting date.

    Thanks.

  • Ludwig Reinhard Profile Picture
    Ludwig Reinhard Microsoft Employee on at
    RE: Committed date in Project accounting

    Good morning marypeace,

    Have you done some additional testing?

    Did you get the same result in the committed cost form or something different?

    Best regards,

    Ludwig

  • Ludwig Reinhard Profile Picture
    Ludwig Reinhard Microsoft Employee on at
    RE: Committed date in Project accounting

    Can you possibly double/triple check your first example.

    I really wonder why a different date was taken.

    Just to be absolutely sure that things work as you expect ...

    And as usual, if there is nothing else left open / unanswered, please verify the answers.

    Many thanks and best regards,

    Ludwig

  • marypeace Profile Picture
    marypeace 520 on at
    RE: Committed date in Project accounting

    Hi Ludwig,

    I replicate it in demo environment but when I replicate it in client's dev environment, you're right it is the accounting date.

    Thanks a lot.

  • Suggested answer
    Ludwig Reinhard Profile Picture
    Ludwig Reinhard Microsoft Employee on at
    RE: Committed date in Project accounting

    Hello marypeace,

    In my case its the accounting date in the PO that drives this.

    Do you see the same issue in a different demo/test environment? In other words, can you replicate it?

    Best regards,

    Ludwig

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

December Spotlight Star - Muhammad Affan

Congratulations to a top community star!

Top 10 leaders for November!

Congratulations to our November super stars!

Tips for Writing Effective Suggested Answers

Best practices for providing successful forum answers ✍️

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 291,280 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 230,214 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Product updates

Dynamics 365 release plans