Hey all
One of our clients had an issue this morning with using up the current number sequence in Sales Orders. The order type got to EW9999, and then didn't roll over to 1000 (that's another issue ...) This was updated manually and is now working fine.
Now when they try to run the Process Manager it will process one or two orders, and then crash with the message " Another process has already added the soplan item, the program must be terminated"
I've re-run the OM Integrity to rebuild the SOPlan table three times today, and each time it processes a couple of orders and then crashes.
I took a look at the SQL SOPlan table, and there are a few lines in there that were created today, that have no CpnyID and the planref = 0000. The rebuild doesn't appear to be getting rid of these. Is it safe to delete these lines?
Any ideas on what else might be going on here?
Thanks, Allison.
*This post is locked for comments