I am getting margin showing in the planned order explosion window. (Master planning > Common > Planned orders > 'View' tab > 'Requirements' button group> 'Explosion' button > 'Gantt' tab). I have checked all the items involved. None of the coverage groups or plans has any margin setup (all values are set to zero).
Is there any other place from where the margin is coming into the planned order?
I know master planning fetches information from lot of setups. Please let me know areas which you suspect.
*This post is locked for comments
Hi,
How long is the margin that is being pulled through?
Does the working calendar have specific days set up whereby production, for example, cannot begin within these days as the 'Working times' is checked within the Master Planning form?
Thanks