Hello,
I am trying to generate Planned Batch Orders of the Formula Item after I have generated a requirement for the Co-Product.
It seems I am setting something wrong, because I have followed the example of the demo data, using P0002 as a Co-Product of P0001.
- In the Co-Product the Formula Item is set in the planning formula field:
- The Formula of the formula Item is Active and Approved
- Default order Setting is Production for both items.
- The Feature for Process Manufacturing support in Planning Optimization is activated.
The system keeps generating a Planned Batch Order for the Co-Product and not for the formula Item.
Additional information, I am trying to do this in version 10.0.33 and working with Planning Optimization in a Cloud environment.
The test performed with Demo Data is an on-premises environment with the old Master planning.
I am wondering whether it is the planning optimization that does not fully support Process Manufacturing, but I have not found this is one of the feature not yet implemented.
Anyone is having the same Issue?