why I cannot adjust expense transaction in Project module ?

(0) ShareShare
ReportReport
Posted on by 1,257

Dear All,

I posted two transaction - type 'Hour' and type 'Expense' to the project type 'Time & Material'. I didn't create invoice proposal. Then I'd like to adjust both of them to 0. I created adjustment. For transaction 'Hour' - I corrected hour qty to 0 and posted adjustment. AX posted it and created reversed transaction and new transaction with qty = 0. So far - so good. Then I tried to do the same with 'Expense' transaction. I adjusted it, corrected qty to 0 - and when posting - AX generated the following error:

2017_2D00_07_2D00_14-16_5F00_03_5F00_05_2D00_Clipboard.png

Why 'Hour' transaction was adjusted but 'Expense' transaction generates error of wrong balance ? 

Any suggestion/help kindly appreciated :)

Witold Adamiak

*This post is locked for comments

I have the same question (0)
  • Suggested answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at
    RE: why I cannot adjust expense transaction in Project module ?

    Hi Witold Adamiak,

    It is difficult to say why this message is triggered. It might be related to a system bug. Have you already checked the available hotfixes on LCS?

    If you need a quick fix, then I would recommend that you post another offsetting expense voucher to your project. That might be the simplest and fastest way to get this resolved.

    Best regards,

    Ludwig

  • SYNAPIS IT Profile Picture
    1,257 on at
    RE: why I cannot adjust expense transaction in Project module ?

    Thanks Ludwig

    I'll try your advice :0

    Regards

    Witold

  • SYNAPIS IT Profile Picture
    1,257 on at
    RE: why I cannot adjust expense transaction in Project module ?

    Hi Ludwig

    concluding this conversation - I see that for expense transaction any adjustment related to qty and cost price are possible. Especially reducing transaction to 0 (as qty or cost price) is forbidden. Could you confirm that ?

    regards

    Witold

  • Verified answer
    Ludwig Reinhard Profile Picture
    Microsoft Employee on at
    RE: why I cannot adjust expense transaction in Project module ?

    Hi Witold,

    Yes, you are right.

    Adjustments do not allow to reduce a transaction that was posted with a quantity of 1 to a quantity of 0.

    If you want to do that, you need to record a corrective (reversal) entry.

    Best regards,

    Ludwig

  • SYNAPIS IT Profile Picture
    1,257 on at
    RE: why I cannot adjust expense transaction in Project module ?

    Hi Ludwig

    thanks for answer - and it would finish my question :)

    Regards

    Witold

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Abhilash Warrier – Community Spotlight

We are honored to recognize Abhilash Warrier as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Martin Tocauer Profile Picture

Martin Tocauer 4

#1
Community Member Profile Picture

Community Member 4

#3
Nayyar Siddiqi Profile Picture

Nayyar Siddiqi 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans