Microsoft Dynamics AX (Archived)

Scheduling Flexibility Vs. Tracking Actual Cost

(0) ShareShare
ReportReport
Posted on by 2,696

Folks,

We have a requirement which needs a scheduling flexibility to schedule a job on any of the applicable machines and at the same time would also like to record the actual cost based on the machine used for scheduling.

Let me try to explain with an example:

We have three machines - M1, M2  & M3 and they all belong to different resource groups. 

Note: In our actual scenario there are 60 machines divided among 10 different resource groups.

Per hour Rates:

M1 - $ 10 / Hour

M2 - $ 12 / Hour 

M3 - $ 14/ Hour

Item I1 can be produced either using M1, M2 or M3 and hence we created capability called M1M2M3 and defined all the machines under that capability.

We have linked the cost categories of M1 to the route since M1 is the primary costing resource.

Assuming we have zero material cost and overhead there are three different costs for an Item I1 based on which machine was used to manufactured, and those are:

I1 - M1 - 10

I1 - M2 - 12

I1- M3 - 14 

To simplify we have taken an assumption that all three machines have a same processing speed but actually it varies. 

Question is - with this mapping will AX record the actual manufacturing cost based on the machine selected?

Note that, maintaining machine specific route can be a solution here but we loses the scheduling flexibility and that is something our users does not want to compromise with.

We would really appreciate any direction/pointers here.

Best Regards

-Rahul Shah

*This post is locked for comments

I have the same question (0)
  • Suggested answer
    gkumar Profile Picture
    740 on at

    Hi Rahul,

    I think  in  the Production control parameters you are considering Item + Category  ,instead have you tried considering Item + Workcentre and assign cost categories for each machine so that cost is consumed based up on the workcentre that is utilized.

    Regards,

    Ganesh

  • Weaveriski Profile Picture
    23,620 Moderator on at

    How do you move it from the scheduled M1 to the M2?

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Introducing the 2026 Season 1 community Super Users

Congratulations to our 2026 Super Stars!

Meet the Microsoft Dynamics 365 Contact Center Champions

We are thrilled to have these Champions in our Community!

Congratulations to the March Top 10 Community Leaders

These are the community rock stars!

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
CP04-islander Profile Picture

CP04-islander 39

#2
Michel ROY Profile Picture

Michel ROY 14

#3
imran ul haq Profile Picture

imran ul haq 8

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans