Hi all,
I'm trying to copy projects between legal entities, and I can't copy one in particular. I receive this error: Cannot create a record in Hierarchies (Hierarchy). Hierarchy ID: XXXXXX The record already exists.
Any idea what could it be?
Thanks in advance
Hi Rony,
What exact procedure/functionality are you using to copy the projects?
Hi André,
I'm using the "Copy into legal entity" functionality".
Thanks
I'm missing the information which exact data entity or entities you are using and if you copy into one or multiple legal entities at once.
Is it only failing for one particular project or several or all projects?
Hi André, it happens only with a project... I was trying to copy Projects entity to one legal entity.
Do you have any workflow with Hierarchy in Project?
Thanks,
Hi Jani, not at all.
Did you ever find the solution to this? It seems like the system keeps trying to use the same Hierarchy ID number sequence while increasing the project ID number sequence. I've tried resetting/editing the number sequence to no avail.
yes its a number sequence issue - resetting pre-allocation (on/off) resolves this problem for any load scenario
Under review
Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.
As AI tools become more common, we’re introducing a Responsible AI Use…
We are honored to recognize Abhilash Warrier as our Community Spotlight honoree for…
These are the community rock stars!
Stay up to date on forum activity by subscribing.
CA Neeraj Kumar 2,028
André Arnaud de Cal... 878 Super User 2025 Season 2
Sohaib Cheema 579 User Group Leader