In Dynamics GP 2010 SP3 when a Primary Vendor ID is set on a site in the Item Quantities Maintenance window the MRP calculation settings on the Item Resource Planning Maintenance window seem to be ignored. For instance when set an order point to 200 units and set the Order Quantity Modifier: Multiple to 450 units for a new item with 0 on hand the MRP suggests a PO for 450 units. However, when I assign a Primary Vendor ID on a site in the Item Quantities Maintenance window the MRP calculation suggests a PO for only 200 Units (the Order Point Quantity). Is there another setting I am missing? TIA for any suggestions.