Skip to main content

Notifications

Supply chain | Supply Chain Management, Commerce
Suggested answer

Planning for Groups of Parts

(1) ShareShare
ReportReport
Posted on by 57
Hello, 
 
We have different part numbers for the same part but for each ship-to location (customer plant location). For example: we have 123A01 and 123A02 setup as different part numbers although it's essentially the same part. The only difference between these part numbers is different packaging and labels. We receive the demand from customers separately for each ship-to location. 
 
However, when we run master planning, we get Planned Production Orders for each of these part numbers. Is there any way to group these Planned Production Orders for the "same part" (probably Product Family)? And then have a point where we can decouple these into separate parts to (01, 02 etc.) to be run for production.  
 
Thank you, 
Mayukh 
  • Suggested answer
    Farouk Galal Profile Picture
    Farouk Galal 51 on at
    Planning for Groups of Parts
    This would be not best practice to have two different items for the same product essentially , my
    guess is your requirement can be acheived using external item description
     
     
     
     
    as for decoupling point coverage code , this for building a buffer value profile of min- reorder - max values and making lower level item in the BOM as make to stock in order to reduce the final lead time of a finished good, if this answered you inquiry kindly mark the answer or provide more detail
  • CU03101311-0 Profile Picture
    CU03101311-0 57 on at
    Planning for Groups of Parts
    Hi Laurens,
     
    Thanks for your answer! 
     
    We use separate part numbers because we have different physical packaging for each part number (the box is different and labelling is different for each ship-to location) and we do line side labelling. 
     
    I saw there was a 'Decoupling point' feature that was recently added. Do you think it is possible to use this to decouple the demand from Aggregate Parts (123A) to Specific Parts (123A01, 123A02 etc)? 
     
    Any thoughts are appreciated. 
    Mayukh
     
  • Suggested answer
    lvdtang Profile Picture
    lvdtang 1,915 on at
    Planning for Groups of Parts
    Hello Mayukh,
     
    Why do you have different part numbers as it is essentially the same part?
     
    I think you can manage the packaging requirement with unit conversions:
     
     
     
    The labeling is possible with Warehouse management.  
     
    I don't think it is possible to group planned production orders with different items numbers and degroup/decouple them again. 
     
    Best regards,
    Laurens van der Tang
     

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

News and Announcements

Announcing Category Subscriptions!

Quick Links

December Spotlight Star - Muhammad Affan

Congratulations to a top community star!

Top 10 leaders for November!

Congratulations to our November super stars!

Tips for Writing Effective Verified Answers

Best practices for providing successful forum answers ✍️

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 291,359 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 230,370 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans