AX 2012 Production Scheduling: Run time * qty

(0) ShareShare
ReportReport
Posted on by

Can we some configure Route Times so the system ignores Quantity value while running schedule calculation?

When it takes same number of hours whether the quantity is 1 or 100, how do we configure the Route Run Time?

Initially I set Run Time to 1 hour and process qty to 1, then running the schedule of a production with 10 qty, it gives me 10 hours of estimate time. But in the actual business process, it's still takes jut one hour.

Then I set Run Time to 1 hour and process qty to 100, then, then running the schedule of a production with 10 qty, it gives me 1/10 hour of estimate time...it should be one hour.

I would like to set Run Time to 1 hour for this operation regardless of the qty value.

Is there any way to solve this business problem?

Could you share with me if you have any idea?

 

Best Regards,

 

Ken

 

 

*This post is locked for comments

I have the same question (0)
  • Community Member Profile Picture
    on at
    RE: AX 2012 Production Scheduling: Run time * qty

    Hi Fredrik,

    This worked. Thanks!

  • Community Member Profile Picture
    on at
    RE: AX 2012 Production Scheduling: Run time * qty

    Hi Maxim,

    Thanks!

    It worked!

  • Verified answer
    Fredrik Sætre Profile Picture
    12,644 on at
    RE: AX 2012 Production Scheduling: Run time * qty

    You can get around this if you use only Setup time instead of Process time.

    Setup time is used only once for each production order no matter the quantity.

  • Verified answer
    Maxim Gorbunov Profile Picture
    456 on at
    RE: AX 2012 Production Scheduling: Run time * qty

    It is not possible to define a route that would completely ignore produced quantity during scheduling. However, if you can define a maximum quantity per production order, you can use the Batch formula. Then, for all production orders with quantity equal or less than your maximum quantity, the system will always schedule the same number of hours for this operation.

    To do so, set up your route operation like this:

    Formula = Batch

    Run time = {Fixed time for your operation}

    Process qty. = {Maximum production order quantity}

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Responsible AI policies

As AI tools become more common, we’re introducing a Responsible AI Use…

Andrés Arias – Community Spotlight

We are honored to recognize Andrés Arias as our Community Spotlight honoree for…

Leaderboard > 🔒一 Microsoft Dynamics AX (Archived)

#1
Syed Haris Shah Profile Picture

Syed Haris Shah 9

#2
Martin Dráb Profile Picture

Martin Dráb 2 Most Valuable Professional

#2
Community Member Profile Picture

Community Member 2

Last 30 days Overall leaderboard

Featured topics

Product updates

Dynamics 365 release plans