What information am I supposed to use to populate the Number of Days field in the Item Resource Planning Maintenance card? Basically, what number of days does this field refer to? 

Any feedback would be helpful.

*This post is locked for comments

  • Suggested answer
    Community Member Profile Picture
    Community Member Microsoft Employee on at
    RE: Item Resource Planning Maintenance Card

    I would like to add a point to the above. you can check these things from within GP by clicking the F1 button for any form/field/button you needed information . Note: The help file is only available for the GP forms and it is very informative.

  • Suggested answer
    Community Member Profile Picture
    Community Member Microsoft Employee on at
    RE: Item Resource Planning Maintenance Card

    Thank you so much.

    Kari Reagan

  • Verified answer
    soma Profile Picture
    soma 24,406 on at
    RE: Item Resource Planning Maintenance Card

    This field is used for Manufacturing item demand calculated/verification (Manufacturing Resource Planning) and PO generation calculation.

    Number of Days

    This field is available only if the order policy for the item is Period Order Quantity.

    Enter the number of days to be considered in calculations of supply of the item.

    For example, if demand for 30 days should be consolidated into a single order, you’d enter 30.

    To know about the order policy, please have a look on the GP abbreviation.

    Order Policy

    This field is available only for items whose type is Sales Inventory or Discontinued.

    Select the order policy to be used for the item.

    If you select Use PO Gen, the Calculate MRP for the item/site option automatically is cleared. If you’ve identified the site as the master site for the item, the order policy must be Use PO Gen.

    If you select Not Planned, you won’t be able to edit any information for the item or item-site combination in the Purchase Order Generator Item Maintenance window. This option is selected automatically for inactive items.

    Other order policies are available if you’re using Manufacturing. Refer to the Manufacturing documentation for more information.

    The order policy you select determines the fields that are available in this window.

    Hope this helps!!!

  • Verified answer
    Wassim Rahme Profile Picture
    Wassim Rahme 5 on at
    RE: Item Resource Planning Maintenance Card

    The Number of Days is used only by MRP's 'Period Order Quantity' Order Policy.  It is the number of days of demand that MRP will consider when suggesting an order quantity.

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

December Spotlight Star - Muhammad Affan

Congratulations to a top community star!

Top 10 leaders for November!

Congratulations to our November super stars!

Community AMA December 12th

Join us as we continue to demystify the Dynamics 365 Contact Center

Leaderboard

#1
André Arnaud de Calavon Profile Picture

André Arnaud de Cal... 291,240 Super User 2024 Season 2

#2
Martin Dráb Profile Picture

Martin Dráb 230,149 Most Valuable Professional

#3
nmaenpaa Profile Picture

nmaenpaa 101,156

Leaderboard

Featured topics

Product updates

Dynamics 365 release plans