Hi,
I am using progress billing rule on TandM project, where on the project group, the all the costs (Hours, Expense and Item) are set to go to PNL. The chargeable categories on the Billing rule however only has Hours and Item categories to be selected, which is OOTB. For progress billing rule you need to have the project budget created so that the system can calculate the % complete, which i have already created. The budget is in approved state as well.
When i create and post the hours transaction on the project, i could see the hours budget being consumed. When i create the invoice proposal for the same, i could see that the system proposes the appropriate contract value for billing the customer, based on the percent complete. This is what is desirable and which is ok.
However when i create the project PO and post the supplier invoice and then when i run the project invoice proposal, i could see system suggesting no value for the invoice. For this project supplier invoice, the budget can be seen as consumed in the project budget balances. So am i missing any setup, which is not allowing the system to suggest a value based on percent complete for the posted project supplier invoice?
*This post is locked for comments
I have the same question (0)