Hi
When setting a precessor on a WBS template line, I get:
Operation detected 1 invalid predecessor which could set successor end date greater than
I assume, its related to calendar as value after "than" is blank, but there is a std calendar with open hours in project parameters.
How to resolve this issue?
Thanks..