Resource Planning for Projects within BC

(3) ShareShare
ReportReport
Posted on by 188

What is the optimum way to plan and organise Resources for Projects (jobs) within BC? Ideally would like an overall view by Resource and you could drag/drop the project task by day (different timeline) to another resource. Is this achievable in BC?

  • Suggested answer
    Teagen Boll Profile Picture
    3,875 Super User 2026 Season 2 on at

    You can use the project planning lines for scheduling resources but if you want a simple drag and drop function that isn't available out of the box.

     

    Insight works has a free app called Graphical Scheduler: Free Graphical Scheduler for Business Central

     

    You can use this for simple drag and drop scheduling. It's advertised as being for manufacturing but you can use it for projects too. They have a lot of videos and information on setting it up.

     

    Best,

    Teagen Boll, CPA
  • Suggested answer
    Mansi Soni Profile Picture
    10,422 Super User 2026 Season 2 on at

    Hello @Sub Mint ,

    In standard Business Central Projects, you can plan resources through Project Planning Lines, assign resources to specific project tasks, define dates/quantities, and review resource capacity/availability. However, the exact drag-and-drop visual planning board by Resource vs. Day/Timeline that you described is not available in standard Project Management. You would typically need a Power BI/Power Apps solution, an extension, or another scheduling tool for that Gantt-style experience.

    https://learn.microsoft.com/en-us/training/modules/set-up-job-planning-lines/
    https://learn.microsoft.com/en-us/training/modules/create-resources/

    Hope this answer helps you!

    Regards,
    Mansi Soni

  • Suggested answer
    Grigorios Mavrogeorgis Profile Picture
    3,363 Super User 2026 Season 2 on at

    Hi, the planning itself is native but the visual part you describe is not. In BC the plan sits on the Project Planning Lines — type Budget, a resource, dates and quantity. That is what feeds resource availability, so first make sure the resources have capacity defined on Resource Capacity, otherwise the availability figures show nothing useful.

    For the overall picture there is the Resource Availability page and the allocated per project matrix, and you can switch the period to day, week or month. It tells you who is over or under booked, but it is a matrix, not a timeline. Moving a task to someone else is just changing the Resource No. on the planning line — works fine, only not by dragging.

    A proper Gantt with drag and drop doesn't exist in standard BC, that needs something on top. Analysis mode or Power BI at least covers the reporting side.

    Glad to help - follow up if anything is unclear.   

    â–º  If this solved it, marking it verified helps others too.       

    Regards,
    Grigorios Mavrogeorgis
    Business Central Consultant & AL Developer

    Work: Gmsoft Limited
    Blog:  insidebusinesscentral
    LinkedIn: linkedin.com/in/gregorymavrogeorgis

  • Suggested answer
    OussamaSabbouh Profile Picture
    19,425 Super User 2026 Season 2 on at

    Hello,

    In standard Business Central, the best approach is to set up each person/machine as a Resource, maintain their Resource Capacity, and assign them to Projects (Jobs) through Project Planning Lines, where you define the resource, planning date, and planned hours; the Resource Capacity Matrix can then give you a day/week/month capacity view, and the Resource Utilization report helps compare capacity against usage. However, the visual experience you describe—resources as rows with project tasks on a timeline that you can drag/drop between dates and resources—is not available out of the box in Business Central Projects. For that requirement, I would keep BC Project Planning Lines as the underlying planning data and use an AppSource scheduling extension or a custom scheduling board that updates those lines when tasks are moved. Microsoft does provide this type of drag-and-drop Schedule Board in products such as Dynamics 365 Project Operations/Field Service, but that is a separate capability from standard Business Central.

    Regards,
    Oussama Sabbouh

  • Suggested answer
    YUN ZHU Profile Picture
    103,125 Super User 2026 Season 2 on at

    You might also want to try the report below; it can be exported to Excel for analysis.

    Thanks

    ZHU

Under review

Thank you for your reply! To ensure a great experience for everyone, your content is awaiting approval by our Community Managers. Please check back later.

Helpful resources

Quick Links

Season of Sharing Community Challenge Winners!

Congratulations to our community stars!

Women in Power Builds Momentum

Expanding mentorship, skilling, and AI innovation

Congratulations to the July Top 10 Community Leaders

These are the community rock stars!

Leaderboard > Small and medium business | Business Central, NAV, RMS

#1
OussamaSabbouh Profile Picture

OussamaSabbouh 674 Super User 2026 Season 2

#2
YUN ZHU Profile Picture

YUN ZHU 362 Super User 2026 Season 2

#3
AndrewThomas81 Profile Picture

AndrewThomas81 359 Super User 2026 Season 2

Last 30 days Overall leaderboard

Featured topics

Microsoft Training Manuals

Product updates

Dynamics 365 release plans